Projects
Safranbolu - Bartın Highway Construction PDF Print E-mail

16 km portion of the Safranbolu-Bartın highway is constructed and there exist,

  • 530.000 m3 earth fill,
  • 225.000 m3 rock excavation,
  • 575.000 m3 excavation and a lot of road structures.

In this construction,

  • 3 moto-scrapers,
  • 2 scrapers,
  • 4 D8 bulldozers,
  • 20 dump trucks,
  • 2 pairs of sheep foot rollers and
  • 2 vibrating cylinders

are used as the construction machinery.

The highway is constructed in 5,5 months on a steep, mountainous and woodland country.

 

 
Ankara - Gökçekaya 380 kv Transmisson Line PDF Print E-mail

 

Installation of transmission lines are in our field of activities, too. 80 km part of 380 kV transmission line between Ankara -Gökçekaya, including the manufacture the towers, are installed and completed.

 

 

 
Maraş - Narlıova 2nd Phrase Irrigation Project PDF Print E-mail

The construction of the Maraş-Narlıova 2nd phase irrigation project is accomplished between 1968 -1971. This project includes the construction of 310.336 m channel, 1.000 m tunnel, 850 m inclined drop, 600 m gallery, 348 m viaduct, 100 m siphon and the construction of 1.118 ea. canal structures. The main phases and the corresponding lengths of construction of 310.336 m channel construction is given below.


The construction of the irrigation project of Maraş Narlıova is accomplished under quite difficult circumstances, because the country is quite steep and mountainous and also the large portion of the area was swamp (historical Mizmilli swamp).

 

 

 

 

 

 

 
Antalya Airport PDF Print E-mail

 

The main features of successfully completed Antalya Airport construction is as follows:

1. The Owner Ministry of Public Works, General Directorate for Construction of Airports and Oil Supply Facilities
2. Date of bid award 23 January, 1973
3. Date of completion 15 May, 1977
4. Main work items  
  a. Runway 3.400 m x 45 m x 0,40 m
  b. Apron 450 m x 225 m x 0,40 m
  c. Taxi route no. I 168 m x 22,5 m x 0,40 m
  d. Taxi route no. II 281,5 m x 22,5 m x 0,40 m
  e. Taxi route no. III 68 m x 22,5 m x 0,40 m
  f. Access and service Roads approx. 50 km
5. Quantities of main works performed:
  a. Total earth moving 1.500.000 m2
  b. Total concrete works 300.000 m2
  c. Cement used 50.000 ton
  d. Fencing approx. 10 km

 

 


 
 

 

 

 
Atatürk (Yeşilköy) Airport PDF Print E-mail


Brief informations concerning the Istanbul-Atatürk Airport (former name Yeşilköy) construction:

1. The Owner Ministry of Public Works, General Directorate for Construction of Airports and Oil Supply Facilities

2. Date of bid award

19 January, 1977

3. Date of completion

15 June, 1980

4. Main work items

 

 

a. Runway

2.300mx 60m x0,35 m

 

b. Cargo apron

150 m x 100 m x 0,35 m

 

c. Taxiways and connections

1.500 m x 22,50 m x 0,35 m

 

d. Ducts for electric cables

10.000 m

 

e. Drainage system

The whole area

5. Quantities of main works:

 

a. Total earth moving

1.000.000 m3

 

b. Total concrete works

235.000 m2

 

c. Asphalt pavement

9.850 ton 

 

d. Cement used

30.000 ton

 

e. Lean concrete

24.500 m3

 

The project involved 2,50 m selected borrow fill, 90 cm thick crushed stone as sub-base and base material and 35 cm of Concrete pavement. Quarry materials were brought form quarries 25 km far to site and crushed at size through a crushing plant, designed and manufactured by ERG. A 100 m3/h capacity batching and mixing plant, also manufacture of ERG, was used for concrete works. Aggregate for concrete was produced through the crushing-screening and washing plants, manufactured by ERG, and sea sand was used. Similar earth moving machinery and equipment, spreader-finisher, joint cutters and joint fillers used at Antalya Airport were also utilized at Yeşilköy.

 


 
 

 

 

 
Kars Airport PDF Print E-mail

 

Brief informations concerning the construction of Kars Airport and infrastructural works:

1. The Owner Ministry of Public Works, General Directorate for Construction of Airports and Oil Supply Facilities
2. Date of bid award 10 February, 1977
3. Date of completion 6 September, 1981
4. Annual working period 4.5 months

5. Main work items:

 

 

a. Runway 

3.500 m x 45 m x 0,35 m

 

b. Apron

130 m x 76 m x 0,35 m

 

c. Service roads

15 km

 

d. Ducts for electrical cables

10.000 m

 

e. Drainage system

approx. 10 km

6. Quantities of main works:

 

a. Excavation

1.000.000 m3

 

b. Embankment

355.000 m3

 

c. Total concrete works

175.000 m2

 

d. Cement used

30.000 ton

 

 

 

 
Karakoçan Dam PDF Print E-mail

 

The Karakoçan dam have been constructed for DSİ in Karakoçan district of Elazığ province including the manufacturing of penstock, valves, gates and other installations.

Purpose

Irrigation

Dam Type

Earthfill

Dam Height

34 m

Crest Length

442 m

Volume of Body

1.037.000 m3

Length of Penstock

345 m

Penstock Diameter

2,50 m

Geologic Form

Agglomerate

Volume of Reservoir

12.500.000 m3

Volume of Irrigation

1.200 H

 

The river had been taken to a conduit and after construction, penstock had been placed to the same conduit. 28.000 m3 rock excavation had been done for the construction of spillway. The main body of dam consists of 1.400.000 m3 earth fill.

Cross-section and general situation of the dam is given which consist of various layers. In the cross-section, impervious clay core, semi-impervious layers at both sides of core, followed by pervious shells, stability fill, filter fill and filling for losses can be observed with different colours. On the general layout plan, one can see the places of dam, penstock, irrigation pipes, reservoir and spillway.

 


 
 

 

 

 
Tercan Dam PDF Print E-mail

 

The scope of construction of dam mainly consists of 2.400.000 m3 filling of various layers, 50.000 m3 concrete which is used for the spillway, power plant building, intake structure and shaft. Also it includes the manufacturing of penstock, valves, gates and trashracks which mean 1.000 tons of manufacturing.

Because of the existence of pervious alluvial around the core of dam, it was difficult to prevent the water seepage to the 24 m deep dam base, in order to place a clay core. It is being very difficult to overcome the seepage of 600 m3/sec water by pumps, as a measure an injection curtain was formed in the alluvium on upstream side. This way the seepage of water was reduced to 250 m3/sec.

 

 

 

 

 

 
Çatalan Dam and HEPP PDF Print E-mail

Çatalan Dam and Hydro Electric Power Plant is located on Seyhan River at about 1 km. downstream of Çatalan Town. It is being constructed for power generation, irrigation and for flood control with an installed capacity of 3 x 65 MW power generation. The dam is of gravity fill type with a volume of 17,5 x 106 m3 earth filling, and the spillway is located on right side of the dam. Crest length and width are 894 m and 12 m respectively. The crest is 130 m in elevation and height of the dam from the foundation is 82 m. There are 2 diversion tunnels located on left side with dimensions of 8,50 m in diameter and 1.777,34 m in length. The annual total power generation of the dam is about 570,10 Gwh.

 

 

 

 

 

 
Karakaya Dam and HEPP PDF Print E-mail
Owner State Hydraulic Works (DSİ) - TURKEY
Location South East of Turkey, on Fırat River
Contractor J.V. Italstrade Torno - ERG for Karakaya
Contract Value U.S. $ 600 x 106  (Civil works only)
Reservoir  
  Volume  9,58 x 109 m3
  Active volume 5,58 x 109 m3
  Maximum elevation 693 m
  Area 29.800 ha.
  Tributary area 80 km2
  Length 166 km
     
Dam Type Arch gravity
  Height 173 m from foundation
  Crest elevation 698 m
  Crest length 462 m
  Concrete volume  2 x 106 m3
  Spillway Crest overstop, 10 ea. 17.100 m3/sec discharge
     
Diversion Tunnels   2 x 11,50 m diameter, circular, 3.500 m3/sec capacity
Power Plant   6 x 300 – 1.800 MVA
Annual output 7,5 x 109 Kwh



 
Artvin - Deriner Dam and HEPP PDF Print E-mail

General Information

Deriner Dam and Hydroelectric Power Plant is located at Artvin province on Çoruh River and the type is double curvature concrete arch dam.

The height of the dam is 253 meters and with this height, the dam is the highest in Turkey and third highest in the world.

The scope of Deriner Dam and HEPP construction includes 40.000.000 m3 of rock excavation, 3.500.000 m3 of dam body concrete, diversion tunnel, underground powerhouse, overflow spillways, access roads and internal roads.  

 

OWNER

State Hydraulic Works (DSİ) - TURKEY

CONTRACTOR

Deriner Consortium - Under the leadership of ERG

PLACE

On çoruh river near Artvin province

PURPOSE

Energy (670 MW, 2.117,75 GWh / year)

CHARACTERISTICS

 

Type

Double curvature concrete

Crest Elevation

397 m

Height

 

from thalweg

202 m

from foundation

253 m

Crest Width

12,00 – 18,00 m

Foundation width

55,00 m

Body concrete

3.500.000 m3

Diversion tunnel

898,14 m

Diversion capacity

1.804 m3/s

Spillway type

Overflow 2 ea.

 

Orifice 8 ea.

Overflow spillway capacity

2.250 m3/s

Orifice spillway capacity

7.000 m3/s

Maximum water elevation

395 m

Total reservoir volume

1.969 x 106 m3

 

 

Powerhouse

Right bank

Type

Underground

Number of units

4

Installed capacity

4 x 167,5 MW (670 MW)

Total energy

2.117,75 GWh

 

 

 

Site Facilities


 

According to the scope of the project, the temporary and permanent facilities, workshops, infrastructural facilities, water supply, wastewater and treatment facilities have been constructed.
 
The facilities have been constructed in 5 different elevation because of the steep slope. The machinery and steel workshops, engine workshop, warehouse, restaurant, crushing-screening plant, concrete plant and the office buildings necessary for DSİ and other consortium members have been located at ERG-1 site at elevation 200 m. The residential buildings for the workers have been located at ERG-2 and the lodgings for engineers and managers, technical office, guest-house, conference hall and local headquarters have been located at ERG-3 and TSE sites. At elevation 650 m, the facilities of DSİ Artvin Regional Directorate have been constructed.
 
 




Plant, Machinery, Equipment List

 

PLANT

 

Steel and Formwork Workshop

10.000 m2

Machine Workshop

30.000 m2

Crushing and Screening Plant

5 ea.

Concrete Plant

5 ea.

Cable Crane

3 x 30 ton

 

 

MACHINERY

 

Bulldozer

20 ea.

Loader

15 ea.

Excavator

20 ea.

Grader

7 ea.

Roller

5 ea.

Truck-mixer

20 ea.

Concrete Pump

9 ea.

Concrete Truck

4 x 30 ton

Drilling Machinery

15 ea.

Truck

50 ea.

Rock Truck

10 ea.

Trailer

7 ea.

Fuel Tanker

8 ea.

Mobile Crane

14 ea.

Truck Mounted Crane

10 ea.

Pick-up

25 ea.

Pickup Truck

25 ea.

Tractor

10 ea.

Bus

10 ea.

Minibus

5 ea.

Jeep

10 ea.

Car

20 ea.

Cement Trailer

30 ea.

Injection Machines

15 ea.

Various Machinery

16 ea.

 

 

EQUIPMENT

 

Concrete Mixer

3 ea.

Generator

22 ea.

Transformer

25 ea.

Water and Injection Pump

80 ea.

Workshop Equipment

30 ea.

Welding Machines

60 ea.

Steel Cut Bend Machines

8 ea.

Concrete Vibrators

35 ea.

Compressors

15 ea.

Electric Compressor

25 ea.

Formwork Systems

10.000 m2

 

 

Applications

DAM EXCAVATION:
The dam body excavation of both right and left bank is totally 13.000.000 m3.

 

 

DAM BODY
The concreting period of 3.500.000 m3 dam body concrete is 1.000 working days. The capacity of each bucket of 3 separate cable cranes used in dam body concreting is 30 tons.

 

DIVERSION:
The diversion of Çoruh River have been completed after the construction of diversion tunnel of 937 m long (incl. inlet and outlet structures) and 11,60 m inner diameter.


 

ANCHORAGE

 

 

RIVER DREDGING

 

 

ROADS:
A by-pass road of 23,5 km has been constructed in order to carry the traffic of existing roads passing through the site area. The length of site internal roads is 37 km.


UNDERGROUND POWERHOUSE:
The dimensions of underground powerhouse is 45 m x 120 m x 20 m and the dimensions of valve chamber is 30 m x 90 m x 10 m.


ELECTROMECHANICS:
The total weight of electromechanical equipment such as turbine, generator, spiral casing, draft-tube, etc. is 8.500 tons.  

 

 

 

COFFERDAMS

 

 

TUNNELS

 

 

POWERHOUSE

 

 

 

Concrete Production Stages

CRUSHING, SCREENING and WASHING PLANT 1000 ton/h
1 BTI hydraulic breaker
2 Vibrating grizzly (48" x 20“)
2 Jaw crusher
1 Triple deck Specmaker screen (6' x 20')
3 Triple deck Vibro/King screen (6' x 20')
3 Gyrasphere crushers
3 Triple deck Specmaker screen (8' x 20')
3 Pioneer vertical shaft impactor
2 Sand sort classifying tank (10' x 40')
1 Single spiral sand prep (44" x 32")
3 Twin spiral sand prep (44" x 32")
7 Vibrating pan feeders (36" x 72")
3 Magnetic belts
64 Conveyors (2.400 m)
PLC control system
 

 

AGGREGATE STORAGE 10.417 m3
5 Underground aggregate silos
10 Vibratory feeders
Transport conveyors
PLC control system
 

 

ICE & CHILLED WATER PLANT
Flake ice plant 210 ton/day
Flake ice storage (240 ton)
Aggregate pre/cooling plant by air
2 Chilled water plant for ice makers
& batch water
Water heating system for winter
PLC control system
 

CONCRETE BATCHING PLANT 360 m3/h
4 Tilting mixers (4 x 4,5 m3)
1 Aggregate silo, 5 bins (1.000 m3)
2 Cement silo (2 x 75 m3)
2 Cement screw conveyor per silo
5 Aggregate batchers
1 Cement batcher
1 Water tank (10 ton)
1 Water batcher
1 Flake ice day tank (1.800 kg)
1 Ice batcher
2 Admixtures tank (800 lt)
2 Admixtures batcher
2 Moisture measuring device
1 Concrete sampling system
Moisture compensation system for aggregates
PLC control system
 

CEMENT STORAGE 4 x 2.300 ton
Diameter 12,4 m
Height 27,4 m
Total weight 520 ton
Pneumatic transport system 150 ton/h
PLC controlled transport system
 


 

CABLE CRANE
Dam body is concreted using 3 cable cranes each having 30 ton capacity and 900 m span. Each machine has an installed capacity of 20 MW and the total necessary energy is 6.000 kW. The volume of buckets used are 4 m3, 6 m3 and usually 9 m3. The total body concrete of 3.500.000 m3 is poured with a capacity of 360 m3/hr.
 



 

 


  

 

 
Bayram - Bağlık Dams PDF Print E-mail

Bayram and Bağlık Dams and Hydroelectric Power Plants (HEPP) are energy purpose integrated dams and they are located in northeast region of Turkey on Çoruh River basin Berta tributary, on the State road connecting Artvin Province Center to Ardahan Province center.
 

The average annual flow of Berta river is about 606x106 m3 (19,20 m3/sec), at Bayram dam site and 786x106 m3 (24,90 m3/sec) at Bağlık dam site.
 

Bayram Dam is Rock fill dam with impervious core and will produce 265 GWh energy annually. Bayram dam will feed Bağlık dam at its downstream by means of a tailrace tunnel of 7.990 m long. Bağlık Dam will be constructed as concrete gravity dam and will produce 238 GWh energy using the water supplied from Bayram reservoir.




 
BAYRAM DAM and HEPP  
RESERVOIR  
High water level 740,00 m
Low water level 686,00 m
Available drawdown depth 54,00 m
Sedimentation level 676,00 m
Gross storage capacity 133 x 106 m³
Effective storage capacity 113 x 106 m³
Reservoir area Maximum 38 km²
   
DAM  
Type Rock fill dam with impervious core
Crest elevation 743,00 m
Thalweg elevation 635,00 m
Cut-off foundation elevation 600,00 m
Height of dam (from foundation) 143,00 m
Height from thalweg 108,00 m
Crest length 388,58 m
Volume of dam body 6.244 x 106 m³
   
DIVERSION TUNNEL  
Diversion capacity 192,00 m³/sec
Location, type, number Left bank, circular, 1 pcs.
Inner diameter 4,50 m
Length 760,37 m
   
SPILLWAY  
Location Left bank
Type Shut with gates
Design flood 1.660 m³/s
Crest elevation 728,00 m
Crest width (incl. mid-pier) 23,00 m
Energy dissipater Energy dissipater basin type III
   
ENERGY TUNNEL  
Type Circular, concrete lined
Number 1
Discharge capacity 43,00 m³/sec
Inner diameter 3,40 m
Length 90,28 m
   
STEEL LINING ENERGY TUNNEL  
Type Steel embedded
Number 1
Inner diameter, length 3,40, 285,52 m
   
TAILRACE TUNNEL  
Type Horseshoe, non-pressure, concrete lined, shotcrete
Max. discharge 43,00 m³/s
Inner diameter (with lining) 4,60 m
Length 7.990 m
Slope 0,00077
   
DEVELOPMENT PLAN  
Intake water level 724,18 m
Tailwater level (1st and 2nd unit) 534,16, 535,75 m
Gross head (1st and 2nd unit) 204,42, 202,83 m
Effective head (1st and 2nd unit) 190,02, 188,43 m
Maximum discharge 43,00 m³/s
   
ANNUAL ENERGY PRODUCTION  
Firm energy 153,50 GWh
Secondary energy 111,50 GWh
Total energy 265,00 GWh
   
   
BAĞLIK DAM and HEPP  
RESERVOIR  
High water level 530,00 m
Low water level 527,00 m
Available drawdown depth 3,00 m
Sedimentation level 517,00 m
Gross storage capacity 7,3 x 106 m³
Effective storage capacity 1,0 x 106 m³
Reservoir area 0,37 km²
   
DAM  
Type Concrete Gravity Dam
Crest elevation 533,00 m
Thalweg elevation 465,00 m
Foundation elevation 459,00 m
Height of dam (from foundation) 74,00 m
Height from thalweg 68,00 m
Crest length / width 198,00 / 5,00 m
Upstream slope 1/0.10 - 1/ .30
Downstream slope 1/0.80
Concrete volume 203 x 103 m³
   
DIVERSION FACILITIES  
Location Left bank
Diversion capacity (Q50) 309,80 m³/sec
Number / Type of tunnel 1 ea. trapezoid section
Width / Height / Length of tunnel 8,00 / 3,20 / 176,54 m
Slope of tunnel 1/0.25 -0.022
   
SPILLWAY  
Location Dam body
Type Chute channel with radial gates
Design flood 1.830 m³/sec
Crest elevation 519 m
Width of spillway crest (incl. mid pier) 27,00 m (pier width 3 m)
Energy dissipater Bucket basin
   
STEEL LINING ENERGY TUNNEL  
Type Steel embedded
Number 1
Discharge capacity 52,00 m³/sec
Inner diameter 3,60 m
Length 201,01 m
   
TAILRACE TUNNEL  
Type Horseshoe, non-pressure, concrete lined, shotcrete
Max. discharge 52,00 m³/sec
Inner diameter (with lining). 4,90 m
Inner diameter (without lining) 6,10 m
Length 4.780 m
Slope 0.00076
Inlet elevation 394,30 m
Outlet elevation 390,67 m
   
DEVELOPMENT PLAN  
Average water level 529,12 m
Tailwater level (1st and 2nd unit) 396,88 -398,73 m
Gross head (1st and 2nd unit) 132,24 -130,39 m
Effective head (1st and 2nd unit) 132,02 -130,17 m
Maximum discharge 52,00 m³/sec
   
ANNUAL ENERGY PRODUCTION  
Firm energy 135,6 GWh
Secondary energy 102,4 GWh
Total energy 238,0 GWh



 
Sivas - Kangal Thermal Power Plant PDF Print E-mail
The Sivas-Kangal Thermal Power Plant is constructed at 25 km from Kangal Town of Sivas and 2 km from lignite coal mines. The Power Plant has been planned to have an installed capacity of 2 x 150 MW at the initial stage and to be extended later to 4 x 150 MW.

“The construction of Coal Preparation, Transportation and Ash Disposal“ works has been undertaken on turnkey basis together with the partners. The work covers 11.000 tons of fabrication of steel constructions and machines together with their transportation, inland transportation of imported materials and equipments, assembling of all 16.000 tons of materials imported or locally fabricated and all civil construction works.

Within the scope of local fabrications are included the total of 12 transfer towers and 50% of 7 mobile equipments consisting of 5 "reclaimers-stackers", 1 stacker and 1 "tripper car". In addition (2x3.500 m) 7.000 m of conveyor line is also included in this scope. 1.900.000 m3 rock excavation 500.000 m3 fill, 49.000 m3 concrete, 2.600 tons of steel and 450.000 m3 crushed stone are included within the scope of civil constructions. Total of the works were completed at the end of 1989.







 
Bingöl - Karlıova Thermal Power Plant PDF Print E-mail
The 1 x 60 MW thermal power plant to be constructed near the town Karlıova 45 kms from Bingöl will be the first one in Turkey from the stand points that it will be built by a consortium under the leadership of a Turkish Company, ERG and further for the first time it will be an integrated project including the development of the coal mine and extraction of coal as well, where it will be built on turn-key basis with 100% credit financing and from the total works over 60% will be executed by the local partner and leader company ERG.

Consortium consists of Waagner-Biro (Austria) to supply the general engineering services, the boiler and its accessories, AEG-Austria and AEG-ETI together to supply and erect the electricals, Skodaexport (Czechoslovakia) to supply the turbine-generator and its accessories, local partner and the leader ERG to supply about 60% from the total fabrications, 100% of civil constructions, erections including erection of turbine generator, inland transportations and local materials and services.

In order to feed this plant with local coal at site all the necessary works are under-taken by an other consortium again under the leadership of ERG wherein VEMB GmbH (Germany) is a consortium partner.







 
Afşin - Elbistan Thermal Power Plant PDF Print E-mail

ERG-VERBUND Elektrik Üretim Şirketi where ERG is the major shareholder, desired to refurbish, desulfurization and construct additional two units to AFŞİN/ELBİSTAN power plant which is the Turkey's largest power plant with capacity of 4 x 344 MW. The scope and objective is take over the existing former power station AFŞİN-ELBİSTAN, together with the coal mine, from the Republic Of Turkey in order to modernize, extend and operate the facility for 20 years. 

After this period, the power plant will be returned as an efficiency-enhanced plant operating at full capacity and generating a  consistent, maximum output.

 

TECHNICAL DATAS  
Number of units
4
Maximum power output per unit
344 MW 
Fuel
Lignite Hu 1.100 kcal/kg
Fuel consumption / scheduled
18 million tons of lignite/year
   
STEAM DATA (fuel load)  
Live steam
1.020 t/h, 535”C, 195 bar
Reheated steam
920 t/h, 535”C, 40 bar
   
TURBINE 1 HP-turbine
  1 IP-turbine and 1 double flow LP-turbine
   
GENERATOR 3.000 rpm
  50 Hz frequency H2 – cooling
   
MAIN TRANSFORMER
 4 of 400 MVA each
  One transformer for 3 phases
   
MAIN COOLING WATER SYSTEM
4 cooling towers, natural draught

 

According to the latest investigations, the brown coal deposits in the AFŞİN-ELBİSTAN area amount to a total of 3.2 billion tons. Thanks to new technologies it will be possible to economically mine 1.8 billon tons in open cast mining operations. The overall deposit spreads out over an area of 120 km2. There are three brown coal deposits suitable for mining within this region. The first of these three deposits is Kışlaköy. Kışlaköy currently supplies the AFŞİN-ELBİSTAN power plant delivering an output of 4 x 344 MW. The total deposits of the Kışlaköy area contain 600 million tons of brown coal suitable for mining.

The brown coal of all three deposit areas will yield a combined thermal value of approximately 1.100 kcal/kg. These deposits contain 44% ash and 56% moisture.

The plant is designed to use low calorie brown coal continuously and safely producing electrical energy without using natural gas or fuel-oil. As an integrated plant with 4 units, the power station and the coal mine will be operated at full output. During peak operations it will be possible to mine an annual 30 million tons of coal and transport approximately 75 million m3 of ash material to the slag heaps.